+9821 88058138 

 

Oil & Gas

Above ground piping

Underground piping

Construction & Erection

Pre Commissioning 

Commissioning 

Commissioning Assistance

 

 

Civil

Excavation and Foundation

Installation of steel structure 

Concrete Tank 

Concrete Cooling Tower

 

 

 

GAS Power Plant

Main and auxiliary cooling system

Construction of Fuel system

Dry cooling system

 

Site preparation ,Civil ,Building ,Mechanical ,Piping , Electrical ,I&C ,Industrial Steel Structure ,Per commissioning of Plant

Owner: Arya Sasol Polymer Co.

Client: Technip France/Nargan Co.

Contractor: Barzin Co.

Location of Project: Assaluyeh

Initial Project estimation: 248,255,828,960 Rls

Capacity: 300,000 tons per year

Project Start Date: Nov 2004